Los Alamitos Unified School District Bond K Project
$126,000,000
Lease/Leaseback Contract with Design Assist
Renovations and Upgrades at 10 Sites
Construction scheduled in five separate phases
Phase two 6/2011 to 9/2012 Hopkinson Elementary School Modernization
$9,500,000 GMP
Project completed $947,000 under budget with $596,000 in contractor savings back to the owner.
15 month construction schedule, phased for occupancy during construction
83,000 square feet of renovations and upgrades.
Construction completed on time, 9-1-12